- Is everyone here
- Open Calendars. Any vacation time coming up?
- Open your todo list of things outside of JIRA, how much time will that stuff take this week?
- Create table of capacity for the week (everyone's total hours avail for sprint work)
- For each person
- Any tasks from last week rolled over into this week?
- move to this week
- How many points left?
- Pick up a story from backlog, estimate points with the whole team. Move to sprint.
- Is this person's sprint full? If not, repeat 2. Else next person.
- Examine each Epic Deadline in this sprint and Re-project expected Delivery Dates using velocity in the Epic from last week